LESCO New Connection Guide Infographic
LESCO New Connection: Documents, Fees & Steps (2026)

LESCO New Connection: Documents, Fees and Step-by-Step Process

By the LESCO Online Bill editorial team · Updated October 2026 · 9 min read

Quick answer: To get a LESCO new connection, submit an application with your CNIC, proof of ownership and a wiring test report to LESCO online or at your sub-division office. LESCO inspects the site and issues a demand notice. Pay it at a bank, and the meter is installed, often within a few days to a few weeks.
Explore LESCO Bill Services

In This Guide

1. What a new connection means 2. Required documents 3. Step-by-step process 4. Connection types and meters 5. Fees and timeline 6. Tenants, shops and special cases 7. Common delays and fixes 8. FAQs

What Is a LESCO New Connection?

A LESCO new connection is an official electricity supply connection for a house, shop, office, factory or farm in LESCO’s service area. LESCO, the Lahore Electric Supply Company, covers Lahore, Kasur, Okara, Sheikhupura and Nankana Sahib, and works under the rules of NEPRA, Pakistan’s power regulator.

Once connected, you get your own meter and a unique 14-digit reference number. That number is used on every bill, so it is worth saving. You can later use it to view your LESCO duplicate bill and make payments.

Who needs to apply?

  • Owners of newly built homes, plots or commercial units.
  • Buyers of property without an active meter.
  • Shop and factory owners starting a business.
  • Tenants who need a separate meter, with the owner’s consent.
  • Consumers who want a higher load or three-phase supply.

Documents Required for a LESCO New Connection

Requirements can vary slightly by category and sub-division, but the core list is similar for most applicants.

DocumentWhy it is needed
CNIC copy of applicantIdentity verification
Proof of ownership (registry, fard, allotment letter, transfer letter)Confirms the right to the property
Wiring test report from a licensed electrical contractorShows the internal wiring is safe
Application formRecords your load and category
Passport-size photographsApplicant record
Owner’s consent and rent agreement (tenants)Permission to install a meter
Commercial or industrial papers (if relevant)Business registration and load details
Pro tip: Make two photocopies of every document and keep the originals handy. Inspection staff sometimes ask to see them on site.

How to Apply for a LESCO New Connection, Step by Step

  1. Complete your wiring. Hire a licensed electrical contractor, finish the internal wiring and get the test report.
  2. Collect your documents. Use the table above as your checklist.
  3. Submit the application. Apply through LESCO’s online channel, or hand it in at your local sub-division office.
  4. Site inspection. A LESCO representative visits to verify the address, load and wiring.
  5. Receive the demand notice. This lists the security deposit and service charges.
  6. Pay at a bank. Use the voucher at a designated bank or an accepted digital channel. Keep the receipt.
  7. Meter installation. LESCO installs the meter and your connection is activated.
  8. Check your first bill. Confirm your reference number, load and category are correct.

Always keep your application number. It lets you follow up with the sub-division or helpline 118.

Types of LESCO Connections and Meters

LESCO classifies connections by use. The category decides your tariff, so choose accurately.

CategoryUsed forTypical supply
DomesticHouses and apartmentsSingle-phase
CommercialShops, offices, plazasSingle or three-phase
IndustrialFactories and workshopsThree-phase
AgriculturalTube wells and farmsThree-phase

Single-phase vs three-phase

Single-phase supply suits normal household use such as lights, fans, fridges and a few air conditioners. Three-phase supply is for heavier loads like large ACs together, machines or motors. If you plan to add more load later, mention it at the start to avoid redoing the connection.

Solar and net metering

If you plan to install solar panels, ask about net metering at the same time. Net metering allows eligible consumers to send surplus electricity back to the grid. Rules and eligibility are set by NEPRA and LESCO, so confirm the current process with your sub-division.

LESCO New Connection Fees and Timeline

There is no single fixed price. The amount depends on your category, sanctioned load and phase. Your demand notice normally includes:

  • Security deposit: held against future bills.
  • Service or connection charges: for processing and installation.
  • Meter and material costs: where applicable.

Pay only the amount printed on the official demand notice, and only through approved bank channels. Rates are revised from time to time, so confirm the current figures with LESCO before you pay.

How long does it take?

Most domestic connections are completed within a few days to a few weeks after fee payment. Commercial and industrial connections can take longer, especially if a transformer or line extension is needed. NEPRA has set service standards for connection times, so you can follow up if the deadline is missed.

Good to know: Pay the demand notice promptly. Vouchers have a validity date, and an expired voucher can delay the whole process.

Special Cases: Tenants, Shops and Plots Without Meters

Can a tenant apply?

Yes. A tenant should bring the owner’s written consent, a copy of the owner’s ownership proof, the rent agreement and their own CNIC. Many tenants prefer their own meter so that bills stay under their control.

Shops and plazas

Commercial users should apply under the commercial category, which has its own tariff. Declaring a domestic connection for business use can lead to penalties during inspection.

Old property with unpaid dues

If the earlier owner left unpaid bills, LESCO may ask for clearance before a new connection. Before buying property, ask the seller for a recent paid bill and check if the LESCO bill is paid or not.

Name change or load change

If you bought a house with an existing meter, apply for a name change instead of a new connection. For more load, apply for a load extension.

Common Reasons for Delays and How to Avoid Them

ProblemWhy it happensFix
Application returnedMissing or unclear documentsRe-submit with a full set of copies
Inspection pendingWrong address or no accessShare a landmark and phone number
Wiring rejectedUnsafe or incomplete workHire a licensed contractor to correct it
Meter not installed after paymentStock or staff delayQuote your application number to the sub-division
Extra money demandedInformal agentsPay only the official demand notice at a bank

Expert insight

The smoothest applications we see have three things in common: complete documents on day one, a licensed contractor’s clean test report, and the receipt kept safely after payment. Avoid middlemen who promise a “fast” connection for extra cash. Official fees are paid only through bank vouchers, and an informal payment gives you no receipt to prove it.

After activation, learn the LESCO bill payment methods so your first bill is paid on time.

Key Takeaways

  • A LESCO new connection needs a CNIC, ownership proof and a wiring test report.
  • The steps are application, inspection, demand notice, bank payment and meter installation.
  • Pick the right category, because it sets your tariff.
  • Pay only official demand notices through approved channels.
  • Tenants need the owner’s written consent.
  • Keep your application number and receipts until the meter is working.

Frequently Asked Questions About LESCO New Connection

How can I apply for a new LESCO connection?

Submit your application online or at your sub-division with your CNIC, ownership proof and wiring test report. Pay the demand notice at a bank and wait for installation.

What documents are required?

A CNIC copy, ownership proof, wiring test report, application form and photographs. Tenants also need the owner’s consent.

How long does it take to get a connection?

Often a few days to a few weeks after fees are paid, depending on load and site conditions.

How much does a new connection cost?

It depends on category and load. Your demand notice lists the exact charges, so confirm them with LESCO.

Can a tenant get a LESCO connection?

Yes, with the owner’s written consent, ownership documents, rent agreement and the tenant’s CNIC.

What should I do after my connection is activated?

Save your reference number, check your first bill and set up a payment method before the due date.

About the Author

Written by the LESCO Online Bill editorial team. We have spent years helping consumers across Punjab understand electricity bills, connections and payment channels. This guide draws on information from LESCO, the Power Division and NEPRA. Rules and fees change, so confirm final details with your LESCO sub-division before applying.

Conclusion

Getting a LESCO new connection is straightforward when you prepare properly: finish safe wiring, gather your documents, apply, pay the official demand notice and keep every receipt. Do that and your meter will be up and running without drama.